Question: an activity on a PERT network has these time estimates: optimistic=2, most likely=unknown, and pessimistic=unknown. if varicane=4 and expected time=6. what are the most likely
an activity on a PERT network has these time estimates: optimistic=2, most likely=unknown, and pessimistic=unknown. if varicane=4 and expected time=6. what are the most likely and pessimistic estimates?
A) 8, 12
B) 5, 14
C) 6, 9
D) 8, 14
E) 5, 12