Question: An Activity On Node ( AoN ) box is used in a Network Diagram. Which of the following quantities on an Activity Node Diagram are

An Activity On Node (AoN) box is used in a Network Diagram. Which of the following quantities on an Activity Node Diagram are equal to the magnitude of the float?
Duration plus Earliest Start Time
Latest Finish Time plus Duration
Earliest Start Time minus Latest Start Time
Earliest Finish Time minus Earliest Start Time
Latest Finish Time minus Latest Start Time