Question: An activity on the project network has a slack time of 0 days. Which of the following is always true? Increasing the activity time by

An activity on the project network has a slack time of 0 days. Which of the following is always true?

Increasing the activity time by 2 days will decrease project duration by 2 days.

Decreasing the activity time by 2 days will increase project duration by 2 days.

Decreasing the activity time by 2 days will decrease project duration by 2 days.

Increasing the activity time by 2 days will increase project duration by 2 days.