Question: An activity on the project network has a slack time of 0 days. Which of the following is always true? Increasing the activity time by
An activity on the project network has a slack time of 0 days. Which of the following is always true?
Increasing the activity time by 2 days will decrease project duration by 2 days.
Decreasing the activity time by 2 days will increase project duration by 2 days.
Decreasing the activity time by 2 days will decrease project duration by 2 days.
Increasing the activity time by 2 days will increase project duration by 2 days.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts