Question: An activity on the project network has a slack time of 2 days. Which of the following is NOT true? Increasing the activity time by

 An activity on the project network has a slack time of

An activity on the project network has a slack time of 2 days. Which of the following is NOT true? Increasing the activity time by 2 days would decrease its slack time by 2 days. Increasing the activity time by 2 days would increase its slack time by 2 days. Increaseing the activity time by more than 2 days would increase the project duration. Increasing the activity time by 2 days would make this activity critical for the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!