Question: An activity that has more than one dependency arrow flowing into it is termed a ( n ) : aburst activity. bparallel activity. cmerge activity.

An activity that has more than one dependency arrow flowing into it is termed a(n): aburst activity. bparallel activity. cmerge activity. dcritical path