Question: An activity that has more than one dependency arrow flowing into it is termed a(n) Select one: a. parallel activity. b. critical path. c. burst
An activity that has more than one dependency arrow flowing into it is termed a(n)
Select one:
a.
parallel activity.
b.
critical path.
c.
burst activity.
d.
merge activity.
e.
independent activity.