Question: An activity that has more than one dependency arrow flowing into it is termed a ( n ) Group of answer choices critical path. merge
An activity that has more than one dependency arrow flowing into it is termed an
Group of answer choices
critical path.
merge activity.
parallel activity.
independent activity.
burst activity.