Question: An activity which had a normal time of 9 weeks and a crashed time of 6 weeks, actually took 11 weeks to complete. What will
An activity which had a normal time of 9 weeks and a crashed time of 6 weeks, actually took 11 weeks to complete. What will happen to the project schedule given that activity has been delayed? a) No impact to project schedule b) Project delayed by 3 weeks c) Project delayed by 2 weeks d) Unknown - not enough information provided