Question: An Agile Team decides they want to use pair programming in future Iterations. Where should this be captured? 1)- In the team's improvement backlog 2)-

An Agile Team decides they want to use pair programming in future Iterations. Where should this be captured?

1)- In the team's improvement backlog

2)- In the Inspect and Adapt meeting notes

3)- In the team retrospective notes

4)- In the Program Backlog