Question: An AON network diagram for Project is shown below. Copy the AON onto your paper and use the given the Activity Expected Times as shown
An AON network diagram for Project is shown below. Copy the AON onto your paper and use the given the Activity Expected Times as shown in the table below to conduct a forward and backward pass on your paper. Then type in your answers to the questions below. (Note that the immediate predecessor(s) shown in the table give the same information as the AON diagram.)

| ACTIVITY | IMMEDIATE PREDECESSOR(S) | ACTIVITY TIME (hours) |
| A | - | 3 |
| B | A | 8 |
| C | A | 7 |
| D | B | 1 |
| E | B | 3 |
| F | C | 5 |
| G | E, D, F | 2 |
State the critical path(s). What is the expected project completion time? hours. What is the slack time of activity D? hours. What is the late finish of activity B? If activity E were delayed by 2 hours, what effect would this have on the project time? If activity C were delayed by 2 hours what effect would this have on the project time? Name an activity that you could be sure would be on the critical path even if you didn't know what the activity times were for any of the activities (but precedence relationships remained the same as shown here).
B E D A G FStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
