An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Job | Description | Predecessor | Expected time in days |
A | Prepare preliminary sketches | NA | 2 |
B | Outline specifications | NA | 1 |
C | Prepare drawings | A | 3 |
D | Write specifications | A B | 2 |
E | Run prints | C D | 1 |
F | Have specifications printed | B D | 3 |
G | Assemble bid package | E F | 1 |