Question: An assembly line with 11 tasks is to be balanced. The longest task is 3 minutes, the shortest task is 1 minutes, and the sum

An assembly line with 11 tasks is to be balanced. The longest task is 3 minutes, the shortest task is 1 minutes, and the sum of the task times is 20 minutes. The line will operate for 600 minutes per day.

a. Determine the minimum cycle time. mins per unit

b. Determine the maximum cycle time. mins per unit

c. Determine the minimum output that is theoretically possible for the line. units per day

d. Determine the maximum output that is theoretically possible for the line. units per day

e. Determine the minimum number of stations needed if the maximum output rate is to be sought. stations

f. Determine the cycle time that will provide an output rate of 150 units per day. mins per unit

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!