Question: An assembly line with 17 tasks is to be balanced. The longest task is 2 minutes, and the total time of all tasks is 16

An assembly line with 17 tasks is to be balanced.
An assembly line with 17 tasks is to be balanced. The longest task is 2 minutes, and the total time of all tasks is 16 minutes. The line operates 480 minutes per day. Management desires to produce 240 units per day. Suppose management formed 9 workstations. What would be the efficiency (%) of this line? (Round your answer to the nearest whole number.) Efficiency =