Question: An assembly process consists of three tasks: Task#1, Task#2, and Task#3. It takes 2 minutes to complete Task#1, 5 minutes to complete Task#2, and 3
An assembly process consists of three tasks: Task#1, Task#2, and Task#3. It takes 2 minutes to complete Task#1, 5 minutes to complete Task#2, and 3 minutes to complete Task#3. The product is assembled in an assembly line with three workers and each worker performs only one task.
Estimate the Throughput Rate (per hour) for this assembly process in a steady state operation.
Step by Step Solution
3.43 Rating (156 Votes )
There are 3 Steps involved in it
Introduction Here we are going to calculate the estimate through out rate per hour for the assembly ... View full answer