Question: An C-bar chart is developed based on data collected from a process. The data is composed of two samples (k=2) of six observations (n=6). The

 An C-bar chart is developed based on data collected from a

An C-bar chart is developed based on data collected from a process. The data is composed of two samples (k=2) of six observations (n=6). The C-Chart is developed with 3 -sigma control limts ( z=3 ). If the Center-Line or c-bar is calculated to be 7.98(cbar=7.98), what is the Upper Control Limit (UCL) for the C-bar chart? 3. 16.69 b. 16.56 c. 16.45 d. 15,89 e. 15.81