Question: An electronics manufacturer makes remote control devices for interactive-cable-TV systems. The following assembly tasks must be performed on each device. Draw the precedence diagram for
An electronics manufacturer makes remote control devices for interactive-cable-TV systems. The following assembly tasks must be performed on each device.
Draw the precedence diagram for this problem, then determine the following:
a. What is the sum of the task times?
A 4.67 minutes
B 5.34 minutes
C 25.9 minutes
D 4.05 minutes
b. What cycle time will allow the production of 200 units over a ten-hour day?
A 1.78 minutes
B 3 minutes
C 3.9 minutes
D 1.5 minutes
c. What is the theoretical number of workstations needed?
A 2
B 1
C 3
D 5
d. Balance this assembly line using the heuristic longest operation time, what is the actual number of stations?
A 1
B 3
C 2
D 5
e. What is the efficiency based on your answer to letter d?
A 35.9%
B 67.5%
C 72.3%
D 85.0%
f. How much idle time is in this process based on the longest operation time?
minutes
A 1.95
B 1.55
C 1.25
D 3.67

Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock