Question: An EPC project, the owner needs to equipt five different machines, five different vendors offered at different prices for machines as the following data; suppose

  1. An EPC project, the owner needs to equipt five different machines, five different vendors offered at different prices for machines as the following data; suppose each vendor will be sellected to supply one machine, assign each equipment to each vendor to minimize and calculate the sum of cost, check your solution:

Machine

1

2

3

4

5

Vendor

A

20

21

19

19

17

B

22

21

20

21

18

C

21

19

18

19

18

D

20

18

19

18

17

E

22

20

20

18

19

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!