Question: An event that must occurs before the performance under a contract is due is best referred to as a ( n ) Condition prerequisite. Condition

An event that must occurs before the performance under a contract is due is best referred to as a(n)
Condition prerequisite.
Condition antecedent.
Condition precedent.
Condition subsequent.