Question: An HR project to implement a new comprehensive hiring tool has four paths: Management wants to be finished two weeks earlier. The following activities can
An HR project to implement a new comprehensive hiring tool has four paths:

Management wants to be finished two weeks earlier.
The following activities can be crashed at these cost:
Slope Max Crashing
B $1,000 2
C $2,000 1
D $500 1
H $300 1
Question: Please crash the project by two weeks on paper and then answer the following question: Which of the following statements are correct? (multiple correct answers)
a. Activity D should be crashed to get from 35 to 34 weeks with the least cost
b. Activity H should be crashed to get from 35 to 34 weeks with the least cost
c. There are 2 critical paths at a completion time of 34 weeks
d. Activities B and D should be crashed to get from 34 to 33 weeks with the least cost
e. Activity D should be crashed to get from 34 to 33 weeks with the least cost
f. There are 2 critical paths at a completion time of 33 weeks
g. Path 1 is never a critical path to achieve 33 weeks
A B C D E F G H Path 1 A G 31 Weeks Path A D H 35 Weeks 2 Path B G 34 Weeks 3 Path B F H 32 Weeks 14Step by Step Solution
There are 3 Steps involved in it