Question: An HR project to implement a new comprehensive hiring tool has four paths: Management wants to be finished two weeks earlier. The following activities can

An HR project to implement a new comprehensive hiring tool has four paths:

An HR project to implement a new comprehensive

Management wants to be finished two weeks earlier.

The following activities can be crashed at these cost:

Slope Max Crashing

B $1,000 2

C $2,000 1

D $500 1

H $300 1

Question: Please crash the project by two weeks on paper and then answer the following question: Which of the following statements are correct? (multiple correct answers)

a. Activity D should be crashed to get from 35 to 34 weeks with the least cost

b. Activity H should be crashed to get from 35 to 34 weeks with the least cost

c. There are 2 critical paths at a completion time of 34 weeks

d. Activities B and D should be crashed to get from 34 to 33 weeks with the least cost

e. Activity D should be crashed to get from 34 to 33 weeks with the least cost

f. There are 2 critical paths at a completion time of 33 weeks

g. Path 1 is never a critical path to achieve 33 weeks

A B C D E F G H Path 1 A G 31 Weeks Path A D H 35 Weeks 2 Path B G 34 Weeks 3 Path B F H 32 Weeks 14

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!