Question: An office complex project is represented by the following activities. Draw an AOA Diagram ( CPM ) for the project AND compute the values of

An office complex project is represented by the following activities. Draw an AOA Diagram (CPM) for the project AND compute the values of ES, EF, LS, LF, FF, and TF for the activities of the project.
\table[[Activity,Predecessors,Followers,\table[[Duration],[(weeks)]]],[A,-,B, C,2],[B,A,D, E,4],[C,A,F,3],[D,B,G,2],[E,B,H,5],[F,C,I,6],[G,D,J,3],[H,E,J, K,4],[I,F,K,2],[J,G, H,L,1],[K,H, I,L,2],[L,J, K,-,1]]