Question: An office complex project is represented by the following activities. Draw an AOA Diagram ( CPM ) for the project AND compute the values of
An office complex project is represented by the following activities. Draw an AOA Diagram CPM for the project AND compute the values of ES EF LS LF FF and TF for the activities of the project.
tableActivityPredecessors,Followers,tableDurationweeksAB CBAD ECAFDBGEBHFCI,GDJHEJ KIFKJG HLKH I,LLJ K