Question: Analysis of a PERT problem shows that expected project completion is 1 0 8 days with a standard deviation of 8 days. There is a

Analysis of a PERT problem shows that expected project completion is 108 days with a standard deviation of 8 days. There is a 0.90 probability that the project will be completed before approximately how many days __________.
Group of answer choices
98
108
109
118

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock