Question: Analysis of a PERT problem shows the expected time for the critical path to be 114 days with a variance of 58. There is a

Analysis of a PERT problem shows the expected time for the critical path to be 114 days with a variance of 58. There is a 0.86 probability that the project will be completed before approximately day x. Write down the value of x to two decimal places.