Question: Analysis of a PERT problem shows the expected time for the critical path to be 114 days with a variance of 58. There is a
Analysis of a PERT problem shows the expected time for the critical path to be 114 days with a variance of 58. There is a 0.86 probability that the project will be completed before approximately day x. Write down the value of x to two decimal places.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
