Question: Analysis of a PERT problem shows the expected time for the critical path to be 118 days with a variance of 50. There is a

Analysis of a PERT problem shows the expectedAnalysis of a PERT problem shows the expected

Analysis of a PERT problem shows the expected time for the critical path to be 118 days with a variance of 50. There is a 0.87 probability that the project will be completed before approximately day x. Write down the value of x to two decimal places. Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 9. Earliest finish time of Bis 25 and earliest finish time of C is 31. Latest start time of Fis 46. Write down the slack for F