Question: Analysis of a PERT problem shows the expected time for the critical path to be 148 days with a variance of 59. There is a
Analysis of a PERT problem shows the expected time for the critical path to be 148 days with a variance of 59. There is a 0.84 probability that the project will be completed before approximately day x. Write down the value of x to two decimal places