Question: ANSWER ALL QUESTIONS. RELATE ALL ANSWERS TO THE CASE STUDY. MRT contractors did not comply with safety SOP, say authorities Initial investigation into the collapse

ANSWER ALL QUESTIONS. RELATE ALL ANSWERS TO THE CASE STUDY.

MRT contractors did not comply with safety SOP, say authorities

Initial investigation into the collapse of the concrete span at the MRT worksite found that the contractors did not comply with standard operating procedures (SOP). Department of Occupational Safety and Health (DOSH) deputy director-general Zabidi Md Adib said safety inspectors found that no engineers or supervisors were present to supervise the installation of the parapet wall.

"The installation of the parapet wall should be supervised by qualified engineers to ensure that it is carried out according to procedures," he said when contacted by Bernama today. DOSH also issued a "Stop Work Order" at the construction site until a complete investigation was carried out while the contractors must provide solutions to prevent a recurrence. "The Stop Work Order is issued to the main contractor, sub-contractors and the project owner, Mass Rapid Transit Corporation Sdn Bhd (MRT Corp)." Zabidi said if the investigation found any violation of the law, then the culprits responsible would be prosecuted in court.

Meanwhile, National Institute of Occupational Safety and Health (NIOSH) chairman Tan Sri Lee Lam Thye said the main issue was the contractors lack of concern for safety. "The issue of safety in the workplace is very important and everyone involved must comply with all procedures to prevent a recurrence." Lee told Bernama a series of unfortunate events involving the MRT would erode public confidence in the public transport project.

Three Bangladeshi construction workers were crushed under 490 tonnes of concrete after the span in Kota Damansara collapsed at 8.30 pm. The three construction workers killed were identified as Mohamed Faruk Khan, Mohammad Elahi Hossain and Mohammad Alauddin Mollik.

Meanwhile, Azhar said the span was intact and properly stressed making it a safe platform to work on. "There were four workers, one was on the ground while three others were on top. I am made to believe and yet to confirm that they had their harness on. "The harness could have prevented them from getting far away from the concrete span causing them to be buried," he told a press conference before announcing his decision to quit as CEO of MRT Corp. Meanwhile, Land Public Transport Commission (SPAD) chairman Tan Sri Syed Hamid Albar said MRT Corp and DOSH were given one week to present their reports. Bernama, August 19, 2014.

Please answer all questions. Please relate all questions to the case above.

1. What are the differences between installation of a machine and inspection of a machine specified under FMA 1967. Discuss. (5 marks)

2. Identify 2 acts the employee did not perform in relative to the duties of employees. (5 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!