Sampling 4 pieces of precision-cut wire (to be used in computer assembly) every hour for the past 24 hours has produced the following results:

Based on the sampling done, the control limits for 3-sigma x overbarx chart are (round all intermediate calculations to three decimal places before proceeding with furthercalculations): Upper Control Limit (UCL Subscript x overbarUCLx) = ? Lower Control Limit (LCL Subscript x overbarLCLx) = ? Based on the x overbarx-chart, the wire cutting process has been IN CONTROL or OUT OF CONTROL?
The control limits for the 3-sigma R-chart are (round all intermediate calculations to three decimal places before proceeding with further calculations): Upper Control Limit (UCL Subscript Upper RUCLR) = ? Lower Control Limit (LCL Subscript Upper RLCLR) = ? Based on the R-chart, the wire cutting process has been IN CONTROL or OUT OF CONTROL ?
Hour R Hour R R 1 2 3 4 5 3.25" 3.10 3.12 3.39 2.97 2.86 0.71" 1.13 1.38 1.26 1.17 0.37 7 8 9 10 11 3.05" 2.65 3.12 2.95 2.83 2.87 0.48" 1.18 0.76 1.28 1.22 0.40 Hour 13 14 15 16 X R 3.21" 0.85" 2.73 1.36 3.22 1.11 2.74 0.45 2.76 1.48 2.64 1.34 Hour 19 20 21 22 23 24 x 3.41" 2.89 2.55 3.38 2.84 2.74 1.56" 1.14 1.03 0.46 1.63 1.02 12 18Step by Step Solution