Question: answer choices: a. .6826 b. .9987 c. .9772 d. .9544 e. .8413 Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic

answer choices: a. .6826 b. .9987 c. .9772 d.answer choices:

a. .6826

b. .9987

c. .9772

d. .9544

e. .8413

Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Precedes Start A,B,C A D 38 90 B E 50 99 100 End 85 A OAG 62 108 115 31 115 68 F 19 25 E 100 End End 91 62 F 65 What is the probability that this project will be completed within 205 days