Question: answer choices: a. .6826 b. .9987 c. .9772 d. .9544 e. .8413 Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic
answer choices:
a. .6826
b. .9987
c. .9772
d. .9544
e. .8413
Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Precedes Start A,B,C A D 38 90 B E 50 99 100 End 85 A OAG 62 108 115 31 115 68 F 19 25 E 100 End End 91 62 F 65 What is the probability that this project will be completed within 205 daysStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
