A project has 55 activities, but only 5 of them are analyzed in this problem. Activity G, IP = not given Activity K, IP = not given Activity M, IP = not given Activity T, IP = G, K, M Activity VIP = M The duration of activity G, K, and M are 40, 31, and 21 days, respectively. It has been calculated that LS(T) = 80 and LS(V) = 88. Find the value of LS(K)