Question: Instructions Question 3 A project has 55 activities, but only 5 of them are analyzed in this problem. Activity G, IP = not given Activity

Instructions Question 3 A project has 55
Instructions Question 3 A project has 55 activities, but only 5 of them are analyzed in this problem. Activity G, IP = not given Activity K, IP - not given Activity M, IP = not given Activity. T, IP = G, KM Activity V, IP - M The duration of activity G, K, and M are 45, 39, and 36 days, respectively. It has been calculated that LS(T) - 79 and LS(V) = 79. Find the value of LS(K).