Question: Question 6 A project has 55 activities, but only 5 of them are analyzed in this problem. Activity G, IP = not given Activity K,

Question 6 A project has 55 activities, but only

Question 6 A project has 55 activities, but only 5 of them are analyzed in this problem. Activity G, IP = not given Activity K, IP not given Activity M, IP = not given Activity T, IP G, K, M Activity V, IP = M = The duration of activity G, K, and M are 37, 47, and 26 days, respectively. It has been calculated that LS(T) = 86 and LS(V) = 85. Find the value of LS(K)