Question: Answer it asap QUESTION 7 Activity Preceding Time A 8 B 3 C 7 A network consists of the activities in the following list. Times

Answer it asapAnswer it asap QUESTION 7 Activity Preceding Time

QUESTION 7 Activity Preceding Time A 8 B 3 C 7 A network consists of the activities in the following list. Times are given in weeks. a. Draw the network diagram. b. Calculate the ES, EF, LS, LF, and Slack for each activity. c. What is project completion time? D , E 4 F. D t 11 Notes TO 1160 3 (1) ENG 20 o