Question: answer me now please Q2: The activities involved in the construction of a certain project are given in the table below. One resource type will
answer me now please
Q2: The activities involved in the construction of a certain project are given in the table below. One resource type will be used during the contract. It is required to schedule the project above so that the daily resource requirements do not exceed 3 labours. (15 degrees) 1. Total project finishing time (2 marks) 2- Critical path diagram (2 marks) 3- Resources bar chart (5 marks) 4- Resources scheduling (6 marks) S Activity Description Dependency Duration (Days) Number of Labours 1 2 3 4 5 6 A B D E F A A A C&D B & E 3 5 5 4 2 3 (Unit/Day) 3 2 1 2 3 2