Question: Answer only A and E B. A network consists of the following list. Times are given in weeks Activity Predecessor Optimistic Most Probable Pessimistic 5
Answer only A and E

B. A network consists of the following list. Times are given in weeks Activity Predecessor Optimistic Most Probable Pessimistic 5 14 B - 3 3 9 C 6 10 14 D . . 3 5 7 E B 4 6 11 F 6 8 G DE 2 1 6 H 3 3 B Draw the network diagram using ADN, e. Calculate the probability that the project will be completed in less than 28 weeks