Question: Answer parts (a) & (b). See the Assembly line below with the following 12 tasks. The desired # of output is 50 units per day.

Answer parts (a) & (b).

See the Assembly line below with the following 12 tasks. The desired # of output is 50 units per day. Balance the assembly line--->Answer parts (a) & (b).

Assume that the system works continuously for 10 hours each day.

Task Task Time (minutes) Preceding task(s)
A 10 -
B 4 A
C 6 B
D 5 -
E 7 B
F 9 B
G 5 C, D
H 4 G
I 2 E
J 3 I, F
K 5 H, J
L 6 K

Answer parts (a) & (b). See the Assembly line

Part (a):

Determine the cycle time (in minutes) for the desired output rate per day.

Part (b):

Balance the line by using the RULE #1: "most number of following task" and then as a SECONDARY RULE: use "shortest operation time" (as a secondary criterion).

Write the sequence of each task in each workstation.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!