Question: Answer parts (a) & (b). See the Assembly line below with the following 12 tasks. The desired # of output is 50 units per day.
Answer parts (a) & (b).
See the Assembly line below with the following 12 tasks. The desired # of output is 50 units per day. Balance the assembly line--->Answer parts (a) & (b).
Assume that the system works continuously for 10 hours each day.
| Task | Task Time (minutes) | Preceding task(s) |
| A | 10 | - |
| B | 4 | A |
| C | 6 | B |
| D | 5 | - |
| E | 7 | B |
| F | 9 | B |
| G | 5 | C, D |
| H | 4 | G |
| I | 2 | E |
| J | 3 | I, F |
| K | 5 | H, J |
| L | 6 | K |

Part (a):
Determine the cycle time (in minutes) for the desired output rate per day.
Part (b):
Balance the line by using the RULE #1: "most number of following task" and then as a SECONDARY RULE: use "shortest operation time" (as a secondary criterion).