Question: Answer please 1.5 What action should the project manager perform when estimating an activity's duration? A. Involve the people who will be performing the work

 Answer please 1.5 What action should the project manager perform when

Answer please

1.5 What action should the project manager perform when estimating an activity's duration? A. Involve the people who will be performing the work to estimate the time they need to complete the activities. B. Use random guessing to estimate durations for all the activities. C. Estimate the duration it will take to complete the activity and include contingencies. D. Authorise the start of the feasibility study phase