Question: Answer the following question? 1. Draw the Activity on Arrow (AOA) networks for the project given below? 2. Determine the Earliest and latest time for

Answer the following question? 1. Draw the
Answer the following question? 1. Draw the Activity on Arrow (AOA) networks for the project given below? 2. Determine the Earliest and latest time for each activity? 3. What is the total project duration? 4. What is the critical path? Following this data Predecessor Duration (day) 0 3 4 Activity Start A B D E F G H 1 Start Start Start A B D 3 2 5 6 4 2 3 4 0 E F,B G, H 1 Finish

Step by Step Solution