Question: Answer the following questions: - How does earned value give a clearer picture of project schedule and cost status than a simple plan versus actual

Answer the following questions:

- How does earned value give a clearer picture of project schedule and cost status than a simple plan versus actual system?

- Schedule variance (SV) is in dollars and does not directly represent time.Why is it still useful?

- In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400.Compute the SV and CV for the project.

- On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560.Compute the SV, CV, and CPI for the project.What is your assessment of the project on day 51?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!