Question: Answer the questions based on the following activity table. a ) What is the minimum cost completion time for this project if the project's baseline
Answer the questions based on the following activity table.
a What is the minimum cost completion time for this project if the project's baseline cost accounts for the sum of activity costs as outlined. Additionally, a fixed cost of $ per day for the project's duration is factored into the normal cost calculation. For any day an activity is expedited crashed the cost increases by the crash cost indicated, plus an additional $ per day for expediting.
b Draw the timecost tradeoff graph for this project and explain your answer for part a
Hint: The crash costs represent the cost of a fully expedited activity. For example, reducing activity B from days to days, costs an extra $ on top of the $ expediting cost for a total cost of $ Reducing B from days to days, costs an extra $ on top of the $ expediting cost, for a total activity cost of $
tableActivityPredecessor,tableNormalTimetableNormalCostCrash Time,Crash CostA$$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
