Question: answer this please A small project was planned to be completed in 40 weeks, with a budget of $360,000, phased equally over the 40 weeks
A small project was planned to be completed in 40 weeks, with a budget of $360,000, phased equally over the 40 weeks ($9,000 per week), with 2.5% of the work to be completed each week. At the end of the first 6 weeks, the project was 12% completed. The following is additional information related to this project: Required-Compute and answer the following (show all your calculations): a) Rate of performance (RP): b) Earned value (EV): c) i) Cost variance (CV): ii) Schedule variance (SV): iii) Cost performance index (CPI): iv) Schedule performance index (SPI): d) Estimate at completion (EAC): e) Estimate to complete (ETC) f) Estimated time to complete (ETTC): g) How is work on the project progressing (be specific, indicating the underlined keyword): i) Is it ahead of schedule or behind schedule? Why do you think so? ii) Is it under budget or over budget? Why do you think so
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts