Question: answer this Question 1 (3 points) A project has three paths running through it. Path Ais 16 days long, Path B is 18 days long,

answer this

answer this Question 1 (3 points) A project has
Question 1 (3 points) A project has three paths running through it. Path Ais 16 days long, Path B is 18 days long, and Path C is 13 days long. Someone tells you, "...we're going to shorten Activity ZZZ by 7 days! We will finish the project so much faster now!" You know that Activity ZZZ is on Paths B and C only. By how much can you expect the project to shorten? (_) 2 days (_) 5 days (_) 4 days (_) 7 days