Question: A project has three paths running through it . Path A is 1 6 days long, Path B is 1 8 days long, and Path
A project has three paths running through it Path A is days long, Path B is days long, and Path C is days long. Someone tells you, we're going to shorten Activity ZZZ by days! We will finish the project so much faster now!" You know that Activity ZZZ is on Paths A and B only. By how much can you expect the project to shorten?