Question: A project has three paths running through it . Path A is 1 6 days long, Path B is 1 8 days long, and Path

A project has three paths running through it. Path A is 16 days long, Path B is 18 days long, and Path C is 14 days long. Someone tells you, "...we're going to shorten Activity ZZZ by 7 days! We will finish the project so much faster now!" You know that Activity ZZZ is on Paths A and B only. By how much can you expect the project to shorten?