Question: Any help will be greatly appreciated with many likes. please if can also show step by step. thanks 2. (25 points) Consider the following Master
Any help will be greatly appreciated with many likes. please if can also show step by step. thanks
2. (25 points) Consider the following Master Production Schedule (MPS) in units: Director labor time per unit of end product: There are two work centers X100 and Y200 involving in the production of A and B. Their historical percentage of usage to produce A and B are Using Overall Factor method of the rough-cut capacity planning to compute for each week: 1. the estimated total required capacity and 2. capacity requirements for X100 and Y200 work centers