Question: any one can solve all question please 1.Construct a network based on the activity descriptions. 2. Find the critical path and the expected project duration.

any one can solve all question please
1.Construct a network based on the activity descriptions.
2. Find the critical path and the expected project duration.
3. Use the Burgess Leveling Procedure to level the resources.
any one can solve all question please 1.Construct
Project 6 Activity Resources Activity VILY (days) A B AH D 2 3 4 F 1R 3 R 2 R 2R TR 2 R 3 R IR 2 R IR D,E,G H 1 2. 3 2 J HI