Question: AOA Case Study # 1 : Given AOA network with duration ( in days ) of each activity answer the 5 questions: The AOA network

AOA Case Study #1: Given AOA network with duration (in days) of each activity answer the 5 questions:
The AOA network graph is given. The length of each activity is given.
Dr. Lin 1
1) What is the critical length?
2) What are the critical activities?
3) What are the non-critical
activities?
4) How many paths are there?
5) State the immediate predecessor(s) for each activity
Activity Immediate
Predecessor(s)
C/NC
A none C
B none NC
C A C
D A,B NC
E C C
F C NC
G D,E C
H F,G C