Question: AOA Case Study #1: Given AOA network with duration (in days) of each activity answer the 5 questions: The AOA network graph is given. The

AOA Case Study #1: Given AOA network with duration (in days) of each activity answer the 5 questions: The AOA network graph is given. The length of each activity is given. ; Dummy Activity 1) 2) 3) 4) 5) What is the critical length? What are the critical activities? What are the non-critical activities? How many paths are there? State the immediate predecessor(s) for each activity