Question: AOA Case Study # 1 : Given AOA network with duration ( in days ) of each activity answer the 5 questions: The AOA network

AOA Case Study #1: Given AOA network with duration (in days) of each activity answer the 5 questions:
The AOA network graph is given. The length of each activity is given.
Dr. Lin 1
1) What is the critical length?
2) What are the critical activities?
3) What are the non-critical
activities?
4) How many paths are there?
5) State the immediate
predecessor(s) for each activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!