Question: AON network diagram: B E H Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Maximum weeks Reduced Crash Cost ($) Activity Crash Cost per

AON network diagram: B E H Normal Time (weeks)

AON network diagram: B E H Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Maximum weeks Reduced Crash Cost ($) Activity Crash Cost per Week ($) A 3 500 2 900 1 400 B 4 600 3 700 1 100 C 6 800 3 1,300 3 166.67 D 6 1,500 4 2,150 2 325 E 6 1,750 4 2.250 N 2 250 F 5 1,200 5 1,200 0 0 F G 7 1,500 5 1,800 2 150 H 3 500 3 500 0 0 Using the information given, (a) Calculate the completion time for this project. Project completion time = weeks. (b) Identify the activities on the critical path. Critical activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!