Question: AON Network Times 6 . From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify
AON Network Times
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
tableIDDescription,Predecessor,TimeASurvey site,None,BExcavate site,ACInstall power lines,BDInstall drainage,BEPour foundation,C D