Question: ne a Project Plan 214 AON Network Times 6. From the following information, develop an AON project network. Complete the forward and backward pass, compute

ne a Project Plan 214 AON Network Times 6. From
ne a Project Plan 214 AON Network Times 6. From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? Predecessor ID Time 5 A B C D E Description Survey site Excavate site Install power lines Install drainage Pour foundation None A B B CD NWA 1 for the custom order project of the Air Control Company is late